News Flash Home
The original item was published from 11/6/2020 10:11:00 AM to 11/6/2020 10:25:44 AM.

News Flash

Current Topics Home Page 1

Posted on: November 4, 2020

[ARCHIVED] Current Construction Projects

constructionzone

Current Construction Projects

  • State Route 82 Widening (pdf)
  • Wallings Road Resurfacing (link) - 11/4/2020 - The County has hired Pavement Technology to install Reclimate on Wallings Road. It is an asphalt rejuvenator that is sprayed on the road. The process should be completed by the end of the week. It will be applied one lane at a time with moving traffic zones. There will be flaggers maintaining traffic. The product will be applied during the day and not during peak hours.
  • Oakes Road Construction Information:

Below is an update on few critical activities that is taking place the week of November 16-20 that will have an impact on both local traffic and site access.

 

Monday (11/9) Pavement removal will begin and patching back the utility trench running down the center of Glenwood. Starting at 8am, all traffic will be diverted and Glenwood will remain closed till the following morning. Note, we will work with any school bus traffic to ensure they are able to access Glenwood prior to 8am that day. The afternoon bus route will only be able to access Glenwood from Route 82 but will not be able to travel through. On Tuesday morning, normal traffic pattern can be resumed.

 

Tuesday (11/10) Oakes Road will be restricted to a single lane for pavement removal and repairs but will be reopened at the end of the work day. We will maintain 2-way traffic during this time.

 

Thursday (11/12) Both Oakes Road and Glenwood will be temporarily closed for short periods of time while our asphalt crew lays the final course of asphalt down. Traffic will be maintained during this work but will be limited during short periods of time. We will also be paving to front entrance to the project on Oaks and will need to utilize Blossom Hill for worker vehicle access. There may be a need to use Blossom for vehicle access on Wednesday while the stone subbase is being installed. All of our subcontractors have beem notified to restrict all deliveries this day. 


Site Construction Issues

The City Engineer and his staff provides consultation to other City Departments, developers, contractors and homeowners on utility and site issues. The Engineer is the first point of contact for questions concerning drainage issues, utility records and roadway improvements. This Department also operates and maintains records of utilities, roadways, and physical geography of the City through a Geographic Information System (GIS) and makes this information available to residents, contractors and developers. 

Engineering Department 440-838-4705


Facebook Twitter Email

Other News in Current Topics Home Page 1

5 snowmen in snow

Be Creative!

Posted on: January 24, 2023
SponsorshipOpportunities

Information

Posted on: January 12, 2023
tax document in the background with AARP Volunteers Needed

AARP Notice

Posted on: December 19, 2022
BANDINQUIRYFORMPIC

Band Inquiry

Posted on: March 7, 2022
Mayor Samuel J. Alai (2)

Mayors Message

Posted on: March 31, 2020
Were Hiring

Join Our Team!

Posted on: February 10, 2022